Construction Phase
Construction is Underway!
A Construction Contract was awarded to NA Monsh out of Morrisville as the lowest bidder. Construction of system components is scheduled to begin at the Wolcott Elementary School in July 2026. The contractors will begin by installing the dispersal zones and a control building.
This will be followed by installation of force main down through the Wolcott Town Forest and School Street. Contractors will begin outreach to homeowners that are connecting to assess plumbing and electrical needs. Work is scheduled to wrap up for the 2026 season around Thanksgiving.
Questions about construction?
Please reach out to the project engineers – Alex Huizenga, alex@stone-env.com.
Final Design and Permitting
The Project is Out to Bid
The project received a Finding of No Significant Impact (FONSI) under the state environmental review process with Vermont DEC. Stone Environmental completed 100% design plans, submitted all state permit applications, and worked with the Town to advertise the project for a competitive bidding process. Bids for the construction of the project will be accepted via email until 4pm on June 19, 2026.
Download the Bid Advertisement »
Seeking New Wolcott Wastewater Commission Members
The Wolcott Wastewater Committee recently announced that we were excited that construction of the new Wolcott Village Wastewater system will begin next week. This seven-year effort will be fully realized and implemented beginning this summer and continuing through next summer. Thanks to all Committee members and our partners: Lamoille Regional Planning Commission, DEC, and Stone Environmental.
For community members interested in serving on the new Wastewater Commission, please contact Select Board Chair Linda Martin at: linda.wolcott.selectboard@gmail.com
Wastewater Ordinance
J.B. Hinds presented the draft Wastwater Ordinance at the January 27 Selectboard meeting (watch on YouTube). The meeting minutes are available in the Selectboard minutes. The Ordinance was adopted by the Selectboard in May 2025.
Download the Wastewater Ordinance »
Moving forward
2025-26 Project Timelines & Milestones
August
August 2025
Committee monthly meeting to discuss easements.
September
September 2025
Committee monthly meeting. 60 % Designs complete.
October
October 2025
EID drafted and submitted for review. All connections identified and easements signed.
November
November 2025
DEC FONSI Public Hearing Scheduled (NEPA).
December
December 2025
DEC FONSI Public Hearing. Project fully permitted. Final Designs complete.
February
February 2026
Project out to bid.
April
April 2026
Construction contractor under contract. Schedule for 2026 construction start, including summer 2026 for disposal fields at elementary school.
July
July 2026
Construction begins!
August
August 2026
Construction of dispersal zones completed at Elementary School.
September
September 2026
Work planned on School Street. Begin assessments at connecting properties.
October
October 2026
Work continues on School Street.
November
November 2026
Work pauses for winter break.
In the news
- Wolcott’s Wastewater Woes to be Washed Away
The Hardwick Gazette – July 2, 2024 - Wolcott voters OK new town sewer, no costs attached
News & Citizen – June 13, 2024 - Wolcott waste watchers will ask voters for newer sewer system
News & Citizen – March 28, 2024 - Governor Scott highlights Wolcott for wastewater project in 2023 inaugural address
State of Vermont – January 5, 2023 - Gov. Scott Announces Release of Nearly $30 Million for Village Water and Wastewater Infrastructure
State of Vermont – October 22, 2022 - Wolcott gets grant for village wastewater infrastructure
News & Citizen – January 3, 2019