Wastewater Committee

Upcoming Events

Construction Phase

Construction is Underway!

A Construction Contract was awarded to NA Monsh out of Morrisville as the lowest bidder. Construction of system components is scheduled to begin at the Wolcott Elementary School in July 2026. The contractors will begin by installing the dispersal zones and a control building.

This will be followed by installation of force main down through the Wolcott Town Forest and School Street. Contractors will begin outreach to homeowners that are connecting to assess plumbing and electrical needs. Work is scheduled to wrap up for the 2026 season around Thanksgiving.

Questions about construction?

Please reach out to the project engineers – Alex Huizenga, alex@stone-env.com.

Final Design and Permitting

The Project is Out to Bid

The project received a Finding of No Significant Impact (FONSI) under the state environmental review process with Vermont DEC. Stone Environmental completed 100% design plans, submitted all state permit applications, and worked with the Town to advertise the project for a competitive bidding process. Bids for the construction of the project will be accepted via email until 4pm on June 19, 2026.

Download the Bid Advertisement »

Seeking New Wolcott Wastewater Commission Members

The Wolcott Wastewater Committee recently announced that we were excited that construction of the new Wolcott Village Wastewater system will begin next week. This seven-year effort will be fully realized and implemented beginning this summer and continuing through next summer. Thanks to all Committee members and our partners: Lamoille Regional Planning Commission, DEC, and Stone Environmental.

For community members interested in serving on the new Wastewater Commission, please contact Select Board Chair Linda Martin at: linda.wolcott.selectboard@gmail.com

Wastewater Ordinance

J.B. Hinds presented the draft Wastwater Ordinance at the January 27 Selectboard meeting (watch on YouTube). The meeting minutes are available in the Selectboard minutes. The Ordinance was adopted by the Selectboard in May 2025.

Download the Wastewater Ordinance »

Moving forward

2025-26 Project Timelines & Milestones

August

August 2025

Committee monthly meeting to discuss easements.

September

September 2025

Committee monthly meeting. 60 % Designs complete.

October

October 2025

EID drafted and submitted for review. All connections identified and easements signed.

November

November 2025

DEC FONSI Public Hearing Scheduled (NEPA).

December

December 2025

DEC FONSI Public Hearing. Project fully permitted. Final Designs complete.

February

February 2026

Project out to bid.

April

April 2026

Construction contractor under contract. Schedule for 2026 construction start, including summer 2026 for disposal fields at elementary school.

July

July 2026

Construction begins!

August

August 2026

Construction of dispersal zones completed at Elementary School.

September

September 2026

Work planned on School Street. Begin assessments at connecting properties.

October

October 2026

Work continues on School Street.

November

November 2026

Work pauses for winter break.

In the news

Thank you for supporting this wastewater system. Slow growth, one step at a time is good for us all.
T. Follert
If we want to have a village, we need wastewater treatment.
G. Young
Thank you to the volunteer committee who has invested five years of research, fundraising, and collaboration with key partners to make this possible for our town.
M. Stadtmueller
Thank you to the volunteer committee who has invested five years of research, fundraising, and collaboration with key partners to make this possible for our town.
A. Wein-Senghas